Solar Project Underway
The Y is getting solar! The project construction timeline is November 30 - December 22. The project includes tree removal and replanting, new A/C units, LED lighting, and covered parking with solar panels for our two main rows of parking.
In order to install the parking stalls, the main parking lot will be fenced and impacted for 3 weeks. 90 spots will be unavailable for the first week, then 45 spots for the next two. Overflow parking will be available in next door at the Eureka Way Building on the corner.
We apologize for any inconvenience and appreciate your patience during this exciting transition.